Gas Transmission Pipelines: Thousands of Kilometres Between Approval and Operation
The Indian regulator Petroleum and Natural Gas Regulatory Board (PNGRB) reported approximately 34,803 km of authorised natural gas pipelines and 28,157 km of operational pipelines as of June 2026 (Picture 1). Compared with June 2025, the operational length increased by 2,728 km. The statistics include not only transmission pipelines but also connection lines and certain regional feeder lines. Authorised and operational lengths must therefore be carefully distinguished from the categories “under construction” and “partially operational.”
One particularly large project is the North-East Natural Gas Pipeline Grid operated by Indradhanush Gas Grid. Of the 1,688 km authorised, only 392 km were operational as of June 2026. On the Mehsana–Bhatinda pipeline, 1,339 km of the 1,943 km authorised were operational. Both projects illustrate the substantial number of pipeline kilometres that are not yet operational.
The eastern gas corridors operated by Gas Authority of India Limited (GAIL) are further advanced. For Jagdishpur–Haldia–Bokaro–Dhamra, including extensions, the PNGRB lists 3,315 operational kilometres out of 3,546 authorised kilometres. On the Srikakulam–Angul pipeline, 470 km of 690 km were operational. The Mumbai–Nagpur–Jharsuguda connection was already largely available, with 1,707 operational kilometres out of 1,755 authorised kilometres.
New Routes and Additional Industrial Connections
Among the more recent projects is the approximately 425-km Kochi–Kanyakumari–Thoothukudi pipeline operated by Indian Oil. The PNGRB approved the project in March 2026 with a capacity of 6.84 million standard cubic metres of natural gas per day. The regulator has set March 2029 as the target completion date. Unlike largely completed corridors, a substantial share of the pipeline construction work on this project is still ahead.
GAIL also lists Gurdaspur–Jammu, Vijaipur–Bina, and Attibele–Bidadi as ongoing projects. Its project overview also includes capacity expansions, replacement pipelines, and connections for industrial customers and city gas networks. However, some of the construction progress figures still refer to November 2025, even though the webpage was updated at a later date. The project list therefore demonstrates the overall work programme but does not provide an up-to-date completion status for every section.
Liquefied petroleum gas (LPG) pipelines also account for a significant share of the market. According to the PNGRB report, 1,437 km of the 2,757 km authorised for Kandla–Gorakhpur were operational as of July 2026. GAIL also lists the capacity expansion of the Jamnagar–Loni LPG pipeline as an ongoing project. Such projects complement natural gas networks but have their own design and operational requirements.